Key activities
The project is testing the economic impact that a variety of flexibility scenarios could have in a future DSO world. The objective is to inform the wider DSO work that is ongoing, especially the TRANSITION and LEO projects.
Expected outcomes
The project will have a variety of benefits including:
- Improving the 11kV network design process by providing insight into automation through Common Information Models (CIM).
- Reducing risk of flexible service procurement through model studies
- Assisting with flexible service investment decision making processes
Funding
NIA £338,600
Start/end date
2019 – 2021
Website
https://project-merlin.co.uk
Project Manager
Rhys Williams