Customer Service
Delivering a safe, resilient and responsive network

NIA SSEPD 0002 Locamation SASensor High-Medium Voltage (HMV) Primary Substation Protection

Key Activities

This project uses a digitised approach where a single processing unit protects the entire substation. It also gives remote access to fault information, which may assist in a reduction of customer minutes lost during power cuts, and provides information which can be used to determine whether maintenance of plant and equipment is required.

Expected Outcomes

Reduction in costs of installation due to reduced hardware and a reduction of costs during storms if details can be extracted remotely about the type of faults that have occurred.

Funding

£28,250

Start/End Date

July 2012 – March 2016

NIA Project Registration and PEA Document – NIA SSEPD 0002 Locamation SASensor High-Medium Voltage (HMV) Primary Substation Protection
NIA Project Registration and PEA Document – NIA SSEPD 0002 Locamation SASensor High-Medium Voltage (HMV) Primary Substation Protection
AuthorColin Mathieson
Publication dateApril 2015
Download
NIA Project Closedown Report – NIA SSEPD 0002 Locamation SASensor High-Medium Voltage (HMV) Primary Substation Protection
NIA Project Closedown Report – NIA SSEPD 0002 Locamation SASensor High-Medium Voltage (HMV) Primary Substation Protection
AuthorColin Mathieson
Publication dateJuly 2016
Download