Delivering a safe, resilient and responsive network

NIA SSEN 0066 Power Supply For Pole Mounted LV Monitoring Devices

Key Activities

The project is developing a prototype 230V power supply solution for wooden pole top LV monitoring where no neutral connection is accessible.

Expected Benefits

To enable LV monitoring equipment to be installed on wooden poles where no neutral connection is accessible.

Progress

Two prototypes of the solution involving the integration of the 230V power supply into a monitor have been produced by Eneida and installed on poles. These are successfully powering LV monitoring equipment, and their performance will continue to be assessed to inform a potential Business as Usual (BaU) deployment.

Project Budget

£75,000

Start/End Date

March 2023 – March 2024

Project Manager

Bob Hopkins